CKD Crushing Plant – Quarry Project

This is a CKD crushing plant project which arrived Penang port on 25th September 2017. Total containers were 19 units consist of GP & special equipments ie flatrack / opentop. Entire clearance/customs inspection/delivery & unloading at site took around 9 days. Installation & test run took almost 3 weeks. Above picture is taken during 80% […]